The extension to Fukuoka City Subway’s Nanakuma Line has been delayed. The huge sinkhole that opened up near Hakata Station last year has put the proposed development behind schedule. The new section of the Nanakuma Line was due to be in operation by 2020 and cost approximately ¥45 billion, but interruptions to the excavation and the reinforcement work that now need to be carried out has seen developers push the expected opening to 2022. The estimated cost of the construction has now risen to ¥58.7 billion. Source: Yomiuri Shimbun, 12/9/2017
Photo: 武1102
Disclaimer: Fukuoka Now posts summaries of Kyushu area related news for the benefit of those who cannot read Japanese. Contents posted here are mostly summaries of publicly posted news stories from Japanese media organizations. Errors might occur during translation. Those errors are ours, and not the news source’s. Photos and images are sourced separately and are for illustrative purposes only. Please use this form to send feedback and questions.